If you’re not using Top Down Estimation you could possibly use the column "Lock Remaining" & give it a new/custom title. This column can be manually ticked or unticked by the user.
Using "Hint Help" on Lock Remaining: "Indicates that the budgeted labor & nonlabor units for the activity will not be modified by top-down estimation"
Just a thought as I’ve never required a tick box (check box) myself.
Member for
18 years 2 monthsRE: Inserting a ’Tick Box’ into a P6 Layout
Mark,
Thanks for the info. It is exactly what I am looking for.
Member for
17 years 4 monthsRE: Inserting a ’Tick Box’ into a P6 Layout
Hi Nigel
If you’re not using Top Down Estimation you could possibly use the column "Lock Remaining" & give it a new/custom title. This column can be manually ticked or unticked by the user.
Using "Hint Help" on Lock Remaining: "Indicates that the budgeted labor & nonlabor units for the activity will not be modified by top-down estimation"
Just a thought as I’ve never required a tick box (check box) myself.
Regards
Mark