WBS Summary

6 replies [Last post]
Arun Vasanth
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Dear Friends
Iam in a big trouble.Please help.

My Manager wants me show the progress in WBS summary only.Means in limited sheets .When I filtered I could see only Planned summary bars only.Please tell me friends how to filter or how to show the actual summary bars also.


Means Planned VS Actual.i want to show both bars.Please tell me the filtering methods..

Awaiting for any ones reply....

With regards
ArunV

Friends please tell me how to filter & show

Replies

Dieter Wambach
User offline. Last seen 8 years 8 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Arun

Sorry, I have no idea of what you really want.

Dieter
Arun Vasanth
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Dear Friends

How we are showing the actual bar of summary bar.

With regards
Arun.V
Arun Vasanth
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Dear Friends

How we are showing the actual bar of summary bar.

With regards
Arun.V
Arun Vasanth
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Dear friends

I want to know the filter method to show summaryActualprogress...


With regards
ArunV
Dieter Wambach
User offline. Last seen 8 years 8 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Arun

Maybe there was a misunderstanding - or I didn’t really get your question.

WBS Summary is an acitity of the type WBS S. In the Gantt chart they will be shown as normal activities. If you’ll have a look at the filter "normal": task- plus resource-dependent plus WBS Summary. Study the help function to learn how to deal with this type. Important: Relationships are ignored.
I don’t know how you measure progress. All the basis for progress measurement, you’ll attach to these activities. Then filter by "Activity Type" equal to.

Hope this helps.

Dieter
Andrew Podolny
User offline. Last seen 1 year 49 weeks ago. Offline
Joined: 16 Nov 2004
Posts: 130
Hi Arun. The easiest way to do this is to open WBS view (menu: Project->WBS). Make sure you have Gantt chart view (menu: View->Show on Top->Gantt Chart). Then right click on Gantt Chart and add Actual and Baseline bars.That’s it.
Regards,
Andrew