“physical % complete” column problem (on WBS summary)

4 replies [Last post]
Izam Zakaria
User offline. Last seen 7 years 19 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Hi

I’ve filled up “physical % complete” for each activity but the problem is it doesn’t display on WBS Summary.
I clicked already the “show grand total” but it’s not happen on “physical % complete” column. Gents what should I do?

Thanks for your attention

Replies

Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Izam,

You must have cost loaded in your programme. Besides, "Physical % Complete" doesn’t roll-up in the summary band, but there is a workaround.

Try to convert your Budgeted Units into Cost by just assigning Price/Unit to the Resource.

Likewise,there is a workaround to convert your "Physical % Complete" into "Performance % Complete" and will roll-up in the Activity & WBS Windows If you have assign Cost to your Task.

Regards,

Arnold
Izam Zakaria
User offline. Last seen 7 years 19 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Arnold

Mine was budgeted units loaded. Do you have any idea?
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Izam,

Your schedule is a resource cost loaded?

Regards,

Arnold
Arnel Lagumbay
User offline. Last seen 11 years 39 weeks ago. Offline
Joined: 31 Aug 2008
Posts: 35
Hi Izam,

Physical % complete will not roll up to WBS summary,my advice is do on excel manually.Try to use Duration&Units percent complete,it will roll up to WBS summary.

I hope it will help...


Best regards,
Arnel