Reference Planning Projects

5 replies [Last post]
Shiva Kumar
User offline. Last seen 11 years 14 weeks ago. Offline
Joined: 11 Nov 2008
Posts: 13
Groups: None
Hi Guru’s,

Can anybody help me to mail me the copies of reference planning projects of High Rise Building / Shopping Mall Projects -- MEP works and Interior Fitout works, as i am moving towards site works as a planner from manufacturing field.

Your immediate reply & help will be highly appreciated..

Thanx in advance GURU’S..

shiva

Replies

Mike Testro
User offline. Last seen 29 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Shiva

Everything depends on your scope of work.

Are you also doing the M&E?

The main interfaces for fit out are:

1. Weathertight.
2. M&E Carcassing - Floors and Ceilings
3. M&E 2nd fix - Floors and Ceilings
4. M&E Commissioning

Common areas and washrooms are a standalone subject and are always a problem - make sure these are planned in detail.

Look out for shared acces routes and trade occupancy at each level.

Rubbish disopsal and hoist time have to be considered.

Other than that it is quite simple.

Best regards

Mike Testro

Shiva Kumar
User offline. Last seen 11 years 14 weeks ago. Offline
Joined: 11 Nov 2008
Posts: 13
Groups: None
hi samer,


thanks for ur information. actually, we are the subcontractor for the interior & fitout works in a high rise building (upto level 41). As i am a beginner to this field, I have to prepare the baseline program from the main contractor’s construction program. so, could u pls assist me in-detailed about the sequences, milestone dates, constraints.

and what are the important things to be considered to prepare the baseline program. while updating, what are the points to be followed with main contractor in order to avoid any delays from our side.

thanks... samer..

shiva
Samer Zawaydeh
User offline. Last seen 6 years 16 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Shiva,

Tell us a small description about the actual project that you are working on and we will try to assist as much as possible.

I would also recommend that you read the information at the following site. It will benefit you greatly.

pmbook.ce.cmu.edu/09_Construction_Planning.html

With best regards,

Samer
Shiva Kumar
User offline. Last seen 11 years 14 weeks ago. Offline
Joined: 11 Nov 2008
Posts: 13
Groups: None
Hi Mike,

Thanks for your reply..

Yes, you are correct.. Just i would like to compare the sequences which i have followed with the others.. that’s why.. if u have any type of project for high rise building, pls. mail me to shivakumaarn@yahoo.co.in

Thanks.

shiva
Mike Testro
User offline. Last seen 29 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Shiva

All projects are different and you have to work out your own sequences on each new project.

If you can’t build then then you can’t plan it.

Good Luck

Mike Testro