Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Integration of the program

3 replies [Last post]
Anand Porle
User offline. Last seen 12 years 14 weeks ago. Offline
Joined: 14 Oct 2009
Posts: 13
Groups: None
Dear all,

I have issue with integration
I mean , Say there 6 to 10 WBS levels are created for each of the funtiona/contractors , if iam getting the updates from them how do i just take all the programs together and assemble in on one my program WBS and get the same data’s what i receive from them.

hope my Q is clear

Replies

R. Catalan
User offline. Last seen 13 years 16 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 314
Groups: None
Anand,

After adding the project to the Master Programme, you have to do the linkage/activity relationships manually, then run.

The next import action shall be "Update Existing Project", then run to check the changes on the sub-project and Master Programme.

Best regards,
R. Catalan
Anand Porle
User offline. Last seen 12 years 14 weeks ago. Offline
Joined: 14 Oct 2009
Posts: 13
Groups: None
Hi Arnold

you have got what i mean. but still one mor step i need to know.
1) i just import that to the Master plan where WBS levels are defined.
2) Once i import them how do i do the interface / link them correspondingly to have over all comparision or final result.

Regs

Anand
Arnold Puy
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Anand,

If I understood your question correctly, you need to create first a project as your Master Plan. In order to build the Master Plan try to gather those data from the Contractor and import all of these. During the import "Import Action" select "Add Into Existing Project".

Regards,

Arnold