Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Calendar Help Please

1 reply [Last post]
Jerry Kirby
User offline. Last seen 14 years 32 weeks ago. Offline
Joined: 10 Apr 2007
Posts: 3
Groups: None
We work a rotating "eight-nines and an eight" schedule.

Week "A" is 5x9s and Week "B" is 3x9s and an eight.

Is there a way to set this up other than manually, week by week?

Thanks.

Replies

Anoon Iimos
User offline. Last seen 2 years 13 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
try to play with "admin preferences"; "user preferences"; "default calendar" and "activity(s) calendar(s)., but you should have "admin superuser priviledge"