Unit/Time Format

1 reply [Last post]
Edniel Recamadas
User offline. Last seen 13 years 21 weeks ago. Offline
Joined: 30 Apr 2009
Posts: 40
Groups: None
Dear All,

Does the unit/time format fixed in hours/day? Or it can be change to i.e. mandays/day, etc.

Urgent help pls.

Thanks

Replies

R. Catalan
User offline. Last seen 12 years 7 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 314
Groups: None
Edniel,

Ideally, unit/time format should be in man-hours/day. But you can change the format settings.

Go to:
1) Admin Preferences - to change the hours per time period
2) Then Edit/User Preferences to change the settings for the unit/time format.

P6 Manual >> "Primavera calculates and stores time unit values in hourly increments. When you display or enter data in time unit fields in increements other than hours, the PM module converts the data based on the hours per time period settings."

Regards,
R. Catalan