Remainig Unit/Time

2 replies [Last post]
moutaz aldeib
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Hi Planners

I am updating a project schedule with resources and after updating I found that the remaining units/time for completed activity is still fixed 8h/d. Is this right? even though the remaining units for that activity is zero.

Best,

Moutaz

Replies

moutaz aldeib
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Thanks Zoltan for your confirmation

Zoltan Palffy
User offline. Last seen 4 days 4 min ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

yes that is corect that does not change