Primavera’s Cand Reporting tool show baseline data

1 reply [Last post]
Kris Herman
User offline. Last seen 14 years 41 weeks ago. Offline
Joined: 8 Jul 2009
Posts: 3

How do you create a single report with Primavera’s own reporting tool to show the per resource baseline hrs vs. the actual hrs? It is so hard trying to use what comes with Primavera. I can show the budgeted hrs or show the per role BL hrs but nothing else.

I know I could look at Oracle-Discovery to generate this required report, but hope someone out there can help me.

Thank you for your reply

Kris

Replies

Khuong Do
User offline. Last seen 14 years 38 weeks ago. Offline
Joined: 22 May 2009
Posts: 27
Groups: None
Hi.
When create a new report, you can choose to show many column which start with BL Project or BL 1... We can show most of data of the baseline.
What kind of field you need to show ?