% complete

2 replies [Last post]
ROHIT RANGNEKAR
User offline. Last seen 14 years 38 weeks ago. Offline
Joined: 29 May 2009
Posts: 47
Groups: None
Dear All,

what is the difference between schedule % complete , duration % complete and activity % complete ?

Regards,

Replies

Tyler Tan
User offline. Last seen 14 years 45 weeks ago. Offline
Joined: 17 Jun 2009
Posts: 4
activity % complete can be choiced in the "general" tab of "activity".
niles luo
User offline. Last seen 12 years 50 weeks ago. Offline
Joined: 25 Nov 2005
Posts: 46
Groups: None
hi,
schedule % complete is calculated base on baseline and data date.
duration % complete=(OD-RD)/OD
activity % complete depends % Complete Type and it should be one of duration,units,physical.

Regards