Storing Activities in P6 then reusing?

10 replies [Last post]
Christopher Nicolas
User offline. Last seen 15 years 3 weeks ago. Offline
Joined: 22 May 2006
Posts: 24
Groups: None
I was told that for activites, or a group that are linked, can be saved into P6, then dumped in by pressing add. Ie if I am working on a new programme and I need to insert all the activities involved in the fitout of a toilet block, I go to an area where I have stored the activities, then paste it into my new programme - anyone know how I do this?

Replies

Christopher Nicolas
User offline. Last seen 15 years 3 weeks ago. Offline
Joined: 22 May 2006
Posts: 24
Groups: None
Its ok, I figured it out
Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

Sorry, I didn’t understood correctly. What do you mean? You want to change the name of the activities?

Christopher Nicolas
User offline. Last seen 15 years 3 weeks ago. Offline
Joined: 22 May 2006
Posts: 24
Groups: None
one more quick question - How do I change the name of the strings of activities I group into Methodology Management - it has a a name I want to change but I can’t figure out how to do it
Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

You are always WELCOME Sir.

Christopher Nicolas
User offline. Last seen 15 years 3 weeks ago. Offline
Joined: 22 May 2006
Posts: 24
Groups: None
THANKS!!!!!

Arnold you’ve done it again - It works a treat - thanks so much.
Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Nicholas,

Go to Start --> Programs --> Primavera --> Methodology Management.

Login Name: "admin"
Password: "admin"

Regards,

Arnold
Christopher Nicolas
User offline. Last seen 15 years 3 weeks ago. Offline
Joined: 22 May 2006
Posts: 24
Groups: None
Arnold - where is Methodology Management? I have exported the file of the activities I need but am not sure how to import it in?

I looked at the plug in / select base and have understood how to ’add’ saved activity groups - just not sure where Methodology Management is?
Dieter Wambach
User offline. Last seen 7 years 1 week ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Christopher

To copy activities I use a different technique.
1. Creat a WBS-node "To_Copy"
2. Copy the required activities into "To_Copy"
3. Goto view "WBS"
4. Copy or move "To_Copy" into the new project
5. Arrange the activities within the new project.

That’s all.

Regards and good luck!
Dieter
Shahzad Ahmad
User offline. Last seen 14 years 39 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
HELLO-MR.PUY

Prob. related to P6

Please advise me as below.

I have made schd. there is % complte type is "Duration" for all activity.

The Schd.i want to update manually with physical % complete.

1. I have to chnage all activity (% complete type) before start updating or one by one i means while updating activity ,then i will change % complete type "duration " in to "physical" then put actual start, % and remaining duration.

in that case updated activity completed/under progress will be
(%Physical) and unupdate activity will be
( % Duration TYpe)

in the P6 manual says have to set at intial stage, means default ..% complete type.

(if i will change % complte type then it has to be same in Baseline & Current Project m I right)

Thanks
Shahzad
Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Christopher,

You need to create a new project in Methodology Management or you can import the project you needed to restore and use it in the future.

Try the following steps:

1. If you have already existing activities or group of activities to be used for future reference, select all the group of activities and save it. delete all the others which is not part of that group. Or you can save everything without deleting the others.
2. After complying the #1, Go to File Menu --> Export.
3. Open the Methodology Management.
4. In the File Menu --> Import the project you exported from Project Management.
5. Then follow the window wizard.

Now you have already finished storing those activities.

Here are the steps on how to re-use or retrieve the group of activites.

1. Go to File Menu --> Project Architect and follow the window wizard.
2. In "Select Base or Plug-in" tick the "Base Methodology" then Next.
3. In Select Base Methodology, select "Select Base"
4. Mark the checkbox next to the "Methodology Name" then close.
5. In "Tailor WBS" select ’Tailor’ you can select the WBS Code you wanted to copy or select the "Activities" to be included by "ticking & unticking" the checkbox.
6. In ’Save Location" select the WBS Element radio button and select or locate the newly added WBS or Activities to your current project.

Hope this helps.

Cheers,