Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

updating and resources in P6

4 replies [Last post]
Brian Yung
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 11 Mar 2009
Posts: 26
Good day ladies and gentlemen,

I am fairly new to scheduling with P6 and I have several questions that I would like to get some clarifications on.

I’ll use the following example to illustrate my issue:
Activity: Concrete Pour
Original Duration: 15 days
Assigned Resources: Formwork, Concrete
Budgeted Formwork: 75m2
Budgeted Concrete: 125m3

Updating:
- I drag the spotlight to my data date (let’s say to the 12th day of the duration)
- I indicate the "Actual Start" date
- I input the actual resource values (formwork: 75m2; concrete 0m3)
- I "schedule" the schedule to the data date

Result:
- I noticed that the bar extends as if the activity has started but nothing has been done.
Actual Duration = 12
Remaining Duration = 15

If I go and change the finish date back to the original planned date, the duration % complete will show 80%

If I go check on the resources, the actual units are not the ones that I have inputed, they basically reflect the duration % complete percentage

formwork: 60m2
Concrete: 100m3

Can anyone help me for these two issues?

Ultimately I would like to:
- show the unit% complete (which remains 0%) all the time
- update the schedule without always changing the finish date of each activity.

I am currently doing tests before actually updating a schedule that has over 3000 activities.


Thanks

Brian

Replies

Dieter Wambach
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Brian

When I started with P3 and later P3e the books of Paul Harris didn’t exist - at least not in Germany. I never read them. The opinions I read in PP is that they are excellent and have many good examples.
Update progress using P6 first needs a concept: Timesheets?, frequency, Progress Spotlight (Y/N), duration types, some project-related parameters - especially under the tab "Resources" -, usage of dates ("planned dates"), ...

Together with P6 a training database with many examples is delivered. Install and use it to test new functions.

Good luck!

Dieter
Brian Yung
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 11 Mar 2009
Posts: 26
Hi Dieter,

You are right about me starting to use a software without going through a manual first. After I realized that there was more than what I thought involved, I started reading a lot of material. One of them is Paul E Harris’ P6 book which I have gone through.

The only thing that I don’t feel comfortable with is updating the schedule.

Unfortunately I don’t have access to P6 now as my pc is going through maintenance. I will look a the topics that you suggested me.


Thanks,

Brian

Dieter Wambach
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Anoon
For my opinion Brian started to use a software without training or study of a manual.

Brian
Your questions are related to the usage of a P6.

Please check the following items in the help-function or the ref-manual:

- Autocompute actuals
- View "Projects" detail tab "resources" --> then "F1"
- Usage of "Spotlight"
- Update progress
- View "Activities" --> detail tab "General" --> check for duration type.

Sorry that I didn’t give the answer you expected but I’m convinced that long term this is the better way.

Good luck!

Dieter

Anoon Iimos
User offline. Last seen 3 years 21 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Hi Brian,

I believe the one who can give best advice on this is Mr. Mike Testro (not to mention C.J.O.). If I may suggest, you break down your activities so as to create always a finish-to-start (FS) link. For example: Your activity "Concrete Pour" can be broken down into the following: 1. Layout -FS-2. Formwork -FS- 3. Reinforcement -FS- 4. Place Concrete. Now you need to define your duration as accurately as possible. Again for example, placement of concrete will take only hours (not days if using pumps).

HTH