IMPORT P3 TO P6 - RESOURCE DICTIONARY UPDATES

1 reply [Last post]
Suresh Sankaranku...
User offline. Last seen 4 years 33 weeks ago. Offline
Joined: 30 Jul 2006
Posts: 77
HI
I tried to import the project from p3 to p6 but the resource dictionary existed in p6 is not getting updated or clashing. Eg: resource id AC in p6 is Acer Dave but the resource id AC in p3 is Azim Chauhan. Now after you import it into p6 the activity where Azim Chuahan assigned shows as Acer Dave. Is there any idea how to deal with it ? Or a Quicker is How can i keep P3 resource seperatly when the same resource id exist in P6.

Suresh

Replies

Dieter Wambach
User offline. Last seen 6 years 48 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Suresh
Resource ID in the database is defined as unique. If you import a project and P6 does find an existing resource, the rules you defined for import will be used: Keep Existing or Insert New (one of the previous you used), Update or Don’t Import. May be a warning from P6 would be appropriate.
To avoid this effect, you’ll have to check for duplicates before. This is from the "Help"-function: "If duplicate resource IDs are encountered during the import process, you can choose how to resolve each conflict by modifying the import configurations in the Import wizard." (End of P6 Help)
Did you read the paragraph under "Import a P3 project" under "Help" already?
Regards
Dieter