P6 - Hours per Timeperiod / Duration

1 reply [Last post]
Oliver Melling
User offline. Last seen 4 years 30 weeks ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine
Does the .1 release for P6 address the issue of incorrect durations being shown when multiple calendars are used, each with differing hours per day?

Replies

David Kelly
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
no. Although at version 6 you can suppress the "incorrect" durations, and use a WBS or LoE activity to show the "correct" ones.