P5 Auot arrange - Need to turn off.

3 replies [Last post]
Stormy J Summers
User offline. Last seen 8 years 14 weeks ago. Offline
Joined: 18 Dec 2006
Posts: 7
Could anyone help with turning the "autoarrange" function off in P5? When I enter a new code value for an activity, the activity jumps to another location w/in the schedule.

Replies

Jiso Thomas
User offline. Last seen 10 years 48 weeks ago. Offline
Joined: 15 Mar 2008
Posts: 15
Can you try to switch off reorganize Automatically in User preference under application caption.It may work for you.

Regards,

Jiso
K D
User offline. Last seen 15 years 28 weeks ago. Offline
Joined: 25 Sep 2007
Posts: 247
Groups: None
Hi.
This feature is available in P6. so you should upgrade to P6.

Regards
Dave Dodds
User offline. Last seen 4 years 26 weeks ago. Offline
Joined: 26 Jul 2006
Posts: 18
Groups: None
From the sounds of it you are grouping by the code you are entering. This will always "autoarrange". If by entering the new code, the activity moves to somewhere you don’t want it, then it is probably the wrong code for that activity.
Try grouping differently.
Cheers.