I am not surpised that you find you have different setting in different projects. My solution is NEVER do "File :new"
Always make a new project by copying a template, which is just a project you have created for just this purpose. It can have the corporate WBS in it, posssibly all those standard activities like "Write safety case" "get three quotes" etc.
All the project level settings AND the scheduling options are copied as well.
Member for
9 years 7 months
Member for9 years7 months
Submitted by Bryon McConnell on Fri, 2018-10-05 18:54
David Kelly, you appear to be exactly on the mark. Looking at the "Resource Assignments" portion of the "Calculations" tab in the Project view, indeed the difference between the projects that work properly and those that don't is the check box "Recalculate Actual Units and Cost when duration % complete changes". I can't explain why it is different from project to project (after all, I built each of them), but now that I know about it, I can manage it. I'll test it out soon.
Thank you for your insight!
Member for
16 years 3 months
Member for16 years3 months
Submitted by Zoltan Palffy on Mon, 2018-10-01 14:08
The primary reason for this is that you are updating the activity's Duration % complete, and at the project window "Calculation" tab - you have "recalculate Actual Units and Costs when Duration % changes" ticked.
You may want on the same Calculation tab to set:
Add Actual to Remaining (to calculate At Completion)
Rather than
Subtract Actual from At completion (to calculate remaining)
Unticking "Calculate costs from units" in the resource dictionary means that the cost of a resource assignment is entered directly rather than calculated as the quantity x the prevailing rate
Auto Compute Actuals is to allow you to pretend that productivity is perfect and everything is on schedule.
Member for
16 years 3 monthsDavid has an excellent Idea
David has an excellent Idea no need to reinvente the wheel every time.
Create a project as a template with all of the correct project settings
calendars including standard holidays
standard codes to be used on all projects
create 1 activity that has the resource that you are going to use with the correct settings
once this is correct use this to start a new project simply by coping it and changing the start date, data date and finish date for the project.
Member for
21 yearsBryon, I am not surpised that
Bryon,
I am not surpised that you find you have different setting in different projects. My solution is NEVER do "File :new"
Always make a new project by copying a template, which is just a project you have created for just this purpose. It can have the corporate WBS in it, posssibly all those standard activities like "Write safety case" "get three quotes" etc.
All the project level settings AND the scheduling options are copied as well.
Member for
9 years 7 monthsDavid Kelly, you appear to be
David Kelly, you appear to be exactly on the mark. Looking at the "Resource Assignments" portion of the "Calculations" tab in the Project view, indeed the difference between the projects that work properly and those that don't is the check box "Recalculate Actual Units and Cost when duration % complete changes". I can't explain why it is different from project to project (after all, I built each of them), but now that I know about it, I can manage it. I'll test it out soon.
Thank you for your insight!
Member for
16 years 3 monthsrun a global
run a global change
tools
global change
new
up top under Select subject area make sure that it says Activity Resource Assignments
then on the right select Add
where calculate costs from units equals yes
then calculate costs from units = no
then on the right select change
then lower right committ
Member for
21 yearsBryon,The primary reason for
Bryon,
The primary reason for this is that you are updating the activity's Duration % complete, and at the project window "Calculation" tab - you have "recalculate Actual Units and Costs when Duration % changes" ticked.
You may want on the same Calculation tab to set:
Add Actual to Remaining (to calculate At Completion)
Rather than
Subtract Actual from At completion (to calculate remaining)
Unticking "Calculate costs from units" in the resource dictionary means that the cost of a resource assignment is entered directly rather than calculated as the quantity x the prevailing rate
Auto Compute Actuals is to allow you to pretend that productivity is perfect and everything is on schedule.