Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Time Scale

6 replies [Last post]
Mirza Imam Baig
User offline. Last seen 5 years 47 weeks ago. Offline
Joined: 29 Apr 2003
Posts: 39
Groups: None
Hello Planners,

Can you please advise me.... whether it is possible to put the time scale at the bottom of the layout in addition to the top one?

Appreciate your inputs. Thanks
Imam Baig

Replies

Frank Borcherdt
User offline. Last seen 7 years 18 weeks ago. Offline
Joined: 3 May 2001
Posts: 88
Groups: None
Not in P5 and nothing in Version 6 beta notes to indicate this is coming.
Mirza Imam Baig
User offline. Last seen 5 years 47 weeks ago. Offline
Joined: 29 Apr 2003
Posts: 39
Groups: None
Thankx for your inputs.

Yeah, it’s possible in P3-3.1. But my question is for P5? Whether this option is still available for P5???
Please advise. Thanks
A D
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
I mean to say, while working in Primavera 3.1, there is no such option, yaa but in page set-up, yes there is an option, and you can see the same in print preview only.

Cheers,

Raviraj
A D
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Sorry Imam,

I dont think so, there is any such option in Primavera 3.1
Andrew Pearce
User offline. Last seen 1 year 13 weeks ago. Offline
Joined: 11 Jun 2001
Posts: 175
Sorry guys,
Perhaps I am having a Senior moment but in P3e I cannot find that option in page set up menu
Ashraf Jahangeer
User offline. Last seen 8 years 6 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Hi Imam,

It is possible to print the schedule with timescale in the bottom.

Command sequence is as follows.

File -> Page Setup -> Timescale Placement -> Select Bottom.


Regards,


Ashraf