limited licensed activities in p3 contractor

1 reply [Last post]
mark johnson
User offline. Last seen 16 years 33 weeks ago. Offline
Joined: 9 Jan 2007
Posts: 12
Groups: None
hi i came across this brick wall while importing into an epc schedule is there any way around it..having unlimited import activites

Replies

Arthur Godbeer
User offline. Last seen 14 years 41 weeks ago. Offline
Joined: 24 Jul 2006
Posts: 127
Groups: None
If you’re asking about limitations on the number of activities in Contractor, then by design Standard is a max of 750 per project and Deluxe is 2000. Project Management in the Planner/Scheduler s/w is unlimited.