Total float

2 replies [Last post]
Rodrigo Brazil
User offline. Last seen 3 years 47 weeks ago. Offline
Joined: 21 Apr 2007
Posts: 3
Hi all,

Is there any way to keep the total float positive when you use "must finish by"?

Rodrigo

Replies

Kevin Button
User offline. Last seen 2 years 18 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 112
Groups: None
Be very careful when using a Mandatory constraint as it ignores all network logic.

KB
Rodel Marasigan
User offline. Last seen 3 days 4 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Hi Rodrigo,

Using Mandatory Finish as your constrain will remove your total float even you have float originally before constraining your activity. If you used mandatory finish dated earlier than schedule then you will have a negative float. This required changing your logic to override your negative float and change it back to 0 float.

Regards,
Rodel