P3e calendar and timescale help

3 replies [Last post]
Adele Botha
User offline. Last seen 17 years 14 weeks ago. Offline
Joined: 18 Jan 2007
Posts: 2
Groups: None
I have activities that are delayed by 4 months or more because of work windows and I’m trying to display the bar differently. I added necking to the bar display options by clicking on the calander nonwork time under the bar settings tab, but now it also necks over weekends and my bars look like sausages. Help please. I’m going crazy. How can I get the bars to neck for my big non work windows and not for weekends.

Replies

Try creating a new calendar for the non work periods and attaching the calendar to the activity.

Regards

Dave
Alex Wong
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
hi

You can add a curtin window to display the non working period

HTH

ALex
Kevin Button
User offline. Last seen 2 years 18 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 112
Groups: None
Adele

What happens if you tick the box for ’Activity nonwork intervals’ rather than ’Calendar nonwork time’? Does this not give you what you need?

KB