Problem of Date

2 replies [Last post]
hengxiang shen
User offline. Last seen 8 years 12 weeks ago. Offline
Joined: 22 Dec 2003
Posts: 7
In my schedule I have one problem as following:

Activity A and B has relationship FS(no lag), Finish date of A is 16-May-07, normally the start date of B is 17-May-07, but in my schedule the start date of B is 16-May-07 same as the finish date of A. In my schedule I have 3 type of calendar but this problem happened if activities have same calendar or not.
Please give me the suggestion.

Thanks,
Shen Hengxiang

Replies

Alex Wong
User offline. Last seen 11 years 3 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
My suggestion is pretty much the same, check the finish activity finish time. if it finish @ 00:59 is different from finish @ 17:59 where you successor will start next date.
Go Edit/User Preferece/Dates/Time/12hr or 24 hrs

HTH

Alex
MK TSE
User offline. Last seen 3 years 45 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
check the planning unit. If all in day, then check the working hour per day.

By default installation, it is 8hr per day. When do progress input by drag on bar instead of type in the value, the result may be fall into some decimal value and cause the problem