In my schedule I have one problem as following:
Activity A and B has relationship FS(no lag), Finish date of A is 16-May-07, normally the start date of B is 17-May-07, but in my schedule the start date of B is 16-May-07 same as the finish date of A. In my schedule I have 3 type of calendar but this problem happened if activities have same calendar or not.
Please give me the suggestion.
Thanks,
Shen Hengxiang
Activity A and B has relationship FS(no lag), Finish date of A is 16-May-07, normally the start date of B is 17-May-07, but in my schedule the start date of B is 16-May-07 same as the finish date of A. In my schedule I have 3 type of calendar but this problem happened if activities have same calendar or not.
Please give me the suggestion.
Thanks,
Shen Hengxiang