Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource driven.

1 reply [Last post]
Marcio Sampaio
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Hello All


Can you help me in understanding the concept of resource driven which we had in P3 3.1, in P3e.


Thanks and regards.

Replies

Marcio Sampaio
User offline. Last seen 11 years 37 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
See this response:

From Primavera:

P3 3.1
Driving resource means a resource that determines the duration of the
activity to which it is assigned. P3 automatically calculates the
activity duration based on the quantity to complete and the units per
timeperiod of the driving resource. P3 schedules independent and
meeting activities using the resource calendars of their driving
resources.
Defining a resource as driving or nondriving in the Resource Dictionary
only establishes its default status; you can change it for any specific
assignment.

P3e
A resource that determines the duration of the activity to which it is
assigned. The Project Management module automatically calculates the
activity duration based on the quantity to complete and the units per
timeperiod of the driving resource.

Defining resources as driving, by marking the Drive Activity Dates by
Default checkbox for new resource assignments in the Projects window,
Project Details, Resources tab, only establishes its default status;
you can change it for any specific assignment.

If an activity has more than one driving resource, the resource that
takes the longest to complete determines the duration of the activity.

Regards

Marcio Eduardo