Steps - P5

4 replies [Last post]
Marcio Sampaio
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Hello all;

Do anyone has experience using STEPS on P5?? I’m a P3e user and i’d like to know advantages of STEPS on P5.

Regards.

Replies

Marcio Sampaio
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Thanks Mario.
Mario Sanvitale
User offline. Last seen 12 years 13 weeks ago. Offline
Joined: 22 Sep 2005
Posts: 139
Groups: None
You can set up Step Templates in V5 for repeatable events.
Marcio Sampaio
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Thanks for your response David.

I normally use STEPS on my schedulles.

But what i would like to know is:

Is there advantages for STEPS on P5 release?

Best regards.

Marcio Eduardo.
Planning & Control - P53
Rio de Janeiro - Brazil
Steps are particularly useful for small activities that do not need to be done in sequence. Each step can be weighted which gives an accurate measure of work completed. A typical example is production of a drawing package


Overall Drawinng 10%
Detailed Drawings 60%
Bill of Materials 5%
Test Specifications 25%