Small Building Projects

3 replies [Last post]
Ahmed Khan
User offline. Last seen 15 years 14 weeks ago. Offline
Joined: 3 Dec 2008
Posts: 29
Hi Planners,

Could any one plz advise me the sequence of activities for a small project for 2400 Sq Ft. (40’x60’) includes the 20 columns (RCC) & Bugdet is around 12 Lakh INR

I am finding the dificulty for making the activity cycle for the above. Basically worked in a huge projects.

If any one have means glad to forward me at "onlyazeem4u@gmail.com"

Thanks

Replies

Tommy Nug
User offline. Last seen 5 years 32 weeks ago. Offline
Joined: 16 Nov 2007
Posts: 44
Hi Maask,

Could you provide me some overviews of the project? I shall help you to work out the schedule.

Cheer,

Tom
Ahmed Khan
User offline. Last seen 15 years 14 weeks ago. Offline
Joined: 3 Dec 2008
Posts: 29
Thank U Mr. Anoon Iimos,

I am expected for the detailed sequence of activities..

Regards

Maask
Anoon Iimos
User offline. Last seen 2 years 18 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
1. Preliminaries (including mobilization)
2. Layout (Survey)
3. Earthworks
4. Concrete Works
4.1 Foundation
4.2 Columns / Beams
4.3 Slabs
5. Architectural Works
6. MEP Works
7. Fit-out
8. Close-out

for task sequencing, you can define it in your schedule