1st Fix, 2nd Fix & 3rd Fix Standard Contains for MEP

4 replies [Last post]
Albert Balogo
User offline. Last seen 9 years 25 weeks ago. Offline
Joined: 9 Jun 2008
Posts: 44
Hello Planners,

Do you have an idea what is the standard contains of work for 1st fix, 2nd fix, and 3rd fix for MEP.


Thanks in Advance

Albert

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

I do not understand ! What counrty does this come from ? We usually do not FIX anything unless it is broken.

If it is not broken don't fix it.

Ahmad Ghidan
User offline. Last seen 8 years 22 weeks ago. Offline
Joined: 17 Jan 2015
Posts: 7

exuse me anyone can help us by any material ?

Samer Zawaydeh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Albert,

1st fix means the empty conduit
2nd fix means the wiring
3rd fix means the sockets and cover plate or equivalent.

Best Regards,

Samer
Anoon Iimos
User offline. Last seen 2 years 13 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
it can mean anything,

for example: Electrical Works, First Fix might be roughing-ins, conduits, supports, sleeves, cable trays etc. Second Fix - wirings, utility boxes, etc. Final Fix - Fixtures, switches, outlets etc.

hth