Budgeted Quantity

1 reply [Last post]
Mohammed Mujtaba
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 31 Aug 2008
Posts: 23
Dear Planners,

After loading the budgeted quantity (manhours), when i add up all the manhours, it is not matching with the manhours in the primavera p3. How to get the exact mhrs in the loading.

Replies

Sajid Balma
User offline. Last seen 12 years 44 weeks ago. Offline
Joined: 8 Jun 2007
Posts: 151
Groups: None
You might have multiple resources assigned to various activities. P3 calculates/adds up the budgeted quantity regardless of their unit. So like if you have 600 cum of concrete and 900 mhr on an activity. P3 will give u a budgeted quantity as 1500.

If you need to make sure that the BQ of mhr and your arthimatic sum is same, run a resource tabular/graphic report on your mhr resource id.