Total Float for the last activity

2 replies [Last post]
moutaz aldeib
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
Dear Planners,

I am preparing time schedule for a project, once I finished I had a look on the massive total float for all the activities, I found some activities have massive total float (activities have no successor), so I started linke those activities to another to alleviate the total float, it was good but suddenly something happened I could not understand it, the last activity in the schedule (project completion date) has got total float (it should be zero)

Could any one tell me what to do?

Regards,

Moutaz

Replies

moutaz aldeib
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
Dear Arnol,

I found out the problem, another activity has got the latest date, not the project completion date.

Thanks a lot,

Moutaz
Arnold Puy
User offline. Last seen 10 years 19 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hello Moutaz,

Try to check your "Project must finish by", in File --> Project Overview. You can remove or change it to the Finish Date of your Project.