Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Project total negative float is less (in absolut value) than some activities' negative float

3 replies [Last post]
oriol manich
User offline. Last seen 8 years 3 weeks ago. Offline
Joined: 22 Jul 2011
Posts: 5
Groups: None

Hi everyone,

I'm using P3 and have a 4500 activities schedule. The problem I'm facing is the following:

The total float of the last activitiy of the project is -10 days, and I have within the program activities with -15 days of total float. I thought that the total float of the project should be at least the same as the lower total float of the activities (so the last activity of the project should show -15 days of total float).

I really don't understand how is this happening and how to solve it, i would appreciate some help.

¡Thanks!

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

have you set a project must fininsh by date ?

check this and make it the same as the constraint date on your last activity.

oriol manich
User offline. Last seen 8 years 3 weeks ago. Offline
Joined: 22 Jul 2011
Posts: 5
Groups: None

Gary, 

Apart from the constraints, what I had was 2 calendars: one with 5 working days a week and one with 7 working days a week. Activities with the 7-working days created a path with less float than the critical path due to the P3 counting 7 days per each week.

Solved!

Thanks for your help!

Regards, 

 

Gary Whitehead
User offline. Last seen 4 years 47 weeks ago. Offline

You have a constraint which is forcing some of your activties to have -15 day float.

 

Go to one of your activities with -15d float, and open the successors. trace the successor which has -15d float, and keep doing this unitl you find the activity with the constraint. remove the constraint and re-schedule.

 

In my opinion it is generally not a good idea to use constraints in your schedule. Especially if you do not understand the effect they have on float.