Best Filter

1 reply [Last post]
Salahuddin Ahmed
User offline. Last seen 7 years 51 weeks ago. Offline
Joined: 1 Apr 2008
Posts: 25
Groups: None
Hi,Guys

I am using P3 and it has got different calenders like 5 days and 6 days, and it has so many constraints due to delivery slippage.

Now the question is "which is the best CPM TF=0 or Longest path".

Appreciate your responce.

And lastly how the filter works in P6 TF or Longest path

Thanks

Salah

Replies

James Barnes
User offline. Last seen 1 year 4 weeks ago. Offline
Joined: 6 Sep 2007
Posts: 243
Longest path has a chequered reputation in P3.1, I don’t have much experience with it but understand that it doesn’t exactly work as advertised.

I use TF=0.

Actually, if you have several "near critical" paths you can go to Tools/options/critical activities and set this to a larger number, I plan in hours and usually set critical activities to be TF<10 hours for critical paths and TF<50 hours to highlight near critical mass work.