How best can I measure Percent Completion of Tasks

1 reply [Last post]
Joel Ogbaji
User offline. Last seen 5 years 14 weeks ago. Offline
Joined: 8 Nov 2007
Posts: 7
How best can I measure Percent Completion of Tasks.
Thanks

Joel

Replies

Prabin Kumar
User offline. Last seen 8 years 24 weeks ago. Offline
Joined: 7 Oct 2005
Posts: 11
Hi Joel,

On level 4 /5 schedule, I used to measure on BOQ basis.
But on Level 3 and below its better to measure on Weight value or Unit (based on cost or resources)

Prabin