Forum Sponsor:

An innovation in P6 Professional training from RPCuk in partnership with Oracle. All the topics that matter to you in workshops customised to your role and industry.  Now get superior training value when you book our Blended Learning Bundle. Learn more here.

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How best can I measure Percent Completion of Tasks

1 reply [Last post]
Joel Ogbaji
User offline. Last seen 39 weeks 5 days ago. Offline
Joined: 8 Nov 2007
Posts: 7
How best can I measure Percent Completion of Tasks.
Thanks

Joel

Replies

Prabin Kumar
User offline. Last seen 3 years 50 weeks ago. Offline
Joined: 7 Oct 2005
Posts: 11
Hi Joel,

On level 4 /5 schedule, I used to measure on BOQ basis.
But on Level 3 and below its better to measure on Weight value or Unit (based on cost or resources)

Prabin