RESOURCES calculation

5 replies [Last post]
MOHAMED nizar
User offline. Last seen 17 years 19 weeks ago. Offline
Joined: 20 Dec 2007
Posts: 6
I am facing in resources calculation to load resources.
For example, what is the resorces compination and quantity needed for 150sm of marble tiling and how to determine the duration. pl help me

Replies

Abhijit Kale
User offline. Last seen 6 years 41 weeks ago. Offline
Joined: 20 Jul 2007
Posts: 126
Groups: None
Dear Friends,
Mangesh! very good answer.

Also you can refer any Civil Engineering Handbook, or there are lot of books available in market for estimating and costing for the geeting the idea abt rate analysis you can use the same.

also if you hace got the time cycles for the previous works you can refer.

cheers,
Abhi
Mangesh Khuspe
User offline. Last seen 1 year 36 weeks ago. Offline
Joined: 10 Apr 2007
Posts: 162
Hi
U r welcome,
There are lots of books available for rate analysis, from which country do u belong coz, the Indian CPWD has its full rate analysis for building works, infrastructure works,
if u r ready to spend indian 2500rs you can get rate analysis softwares readily available.

The CPWD has its own excel sheets for rate analysis & Billing works.

cheers,

Mangesh
MOHAMED nizar
User offline. Last seen 17 years 19 weeks ago. Offline
Joined: 20 Dec 2007
Posts: 6
Dear Mr. Mangesh Khuspe,

Thank you so much for your valuable points. Could you please advise me where can I find complete rate analysis for building works which is not available even in the government departments
Thank you.

MIM. Nizar
Sajid Syed
User offline. Last seen 13 years 43 weeks ago. Offline
Joined: 7 Feb 2008
Posts: 56
hi
can you email me an example case.

Mangesh Khuspe
User offline. Last seen 1 year 36 weeks ago. Offline
Joined: 10 Apr 2007
Posts: 162
Hi
You will need the rate analysis done for quantities, it will give you both, which u can use for loading resources.

Cheers