Change Activity ID in p3

9 replies [Last post]
ASHKAN KHALESI
User offline. Last seen 16 years 45 weeks ago. Offline
Joined: 24 May 2006
Posts: 3
I want to know how can I change all activitiy ID in p3 after defining and finishing project.

Replies

A D
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Thats true,

Oops!! I forget to say that
Edderic See
User offline. Last seen 14 years 17 weeks ago. Offline
Joined: 20 Jul 2005
Posts: 25
Groups: None
Hi Raviraj,

You can also use Copy Ctrl-C then Paste Ctrl-V then using auto increment change the values of your id’s. If the scope of work is repetitive, you can link and load them with resources before copying. That way, when you begin pasting those activities you only need to link the floors. That will also depends on your programmed work cycles.

Regards,

Ed
A D
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
There’s one more easy way to do this.

1. Create a typical cycle for each floor, if u r doing building project, or may be for one particular section, if u doing road / pipeline project. Use only 7 digits for ACTIVITY ID.

2. Link all these activities using appropriate lags with levels assigned to it.

Once this typical cycle is over, then filter NO ACTIVITIES, paste this typcial cycle, and then change the prefix for each floor.

EXAMPLE: (For the project, i m working into)

THERE CAN BE ONLY 10 DIGIT ACTIVITY ID

Lets split that into following for say Building project:

- First 3 digit for each floor. Create Code list for same.
- 1 digit for space, say tower, podium, pool, annex etc.
- 2 digits for specification - type of work involved like concrete, masonary, wood, metal, pre-construction etc.
- 3 digit for the particular activity
- 1 digit for revision

Now create a typical cycle for say structural works and interior fit-out works. Assign them only last seven digits and then paste this cycle every time with required prefix of floor. THIS IS WHAT YOU ASKED, RIGHT?

And the only work now balance is linking floor to floor activities.

THE END :-)

Cheers,

Raviraj
Haris Famil Parol
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 11 Jan 2006
Posts: 12
Groups: None
- First create a new Activity Code (NewID) = 10 Char
- Export ID, Name and NewId
- Create a new ID in NewID (in Excel)
- Import
- use Global Change to replace ID with NewID

Regards

Hannes de Bruyne
05 Sep 2007, 08:11 #4
Mangesh Khuspe
Building Works
Member since Apr 2007

United Arab Emirates (AS.AE)


this one works well, thank u sir :)


--------------------------------------------------------------------------------
Hi
ASHKAN KHALESI

the best thing i have found is to make some changes in p3.ini file.
go to help menu-->search p3.ini--->customize settings-->
in this file u will find all that u want.

cheers

mangesh

thi .ini file helps for few other action like makin a project exclusive wen there no option to do so



thank u all, u made mah day :)
Mangesh Khuspe
User offline. Last seen 29 weeks 5 days ago. Offline
Joined: 10 Apr 2007
Posts: 162
hi
Ashkan
what Paul has said in first is a very nice option.
i always prefer that.
i would like to share something which i have learned.
that in p3 we have activity id limitations upto 10 characters. so even if we activity id of only one character, p3 saves the activity id as 9 blanks and 1 character, so if you want to amend that activity and add somthing into the prefix or suffix, first u will have to remove those blanks and then give the numbering u want.

now this is my assumption.
I would be grateful if our senior planners could just guide me on this, whether i am right or wrong.

cheers

Mangesh
Paul Harris
User offline. Last seen 1 year 6 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618
After backing up your project, your can either:

1. Copy all the activities and then paste them selecting an appropriate renumbering method, then delete the original activities.
2. Use a Global Change.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Hannes de Bruyne
User offline. Last seen 1 year 34 weeks ago. Offline
Joined: 25 Jul 2005
Posts: 154
Groups: None
- First create a new Activity Code (NewID) = 10 Char
- Export ID, Name and NewId
- Create a new ID in NewID (in Excel)
- Import
- use Global Change to replace ID with NewID

Regards

Hannes de Bruyne
Mangesh Khuspe
User offline. Last seen 29 weeks 5 days ago. Offline
Joined: 10 Apr 2007
Posts: 162
Hi
ASHKAN KHALESI

the best thing i have found is to make some changes in p3.ini file.
go to help menu-->search p3.ini--->customize settings-->
in this file u will find all that u want.

cheers

mangesh
Dieter Wambach
User offline. Last seen 7 years 2 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Mark "Exclusive" before you open the project. Then you can modify the id’s
Dieter