changing Activity ID using global change

7 replies [Last post]
Abdelmoneim Youss...
User offline. Last seen 8 years 33 weeks ago. Offline
Joined: 24 Oct 2004
Posts: 21
how can i change Activity ID using global change

Replies

Edgar Ariete
User offline. Last seen 5 years 30 weeks ago. Offline
Joined: 17 Jul 2005
Posts: 184
Hi Abdel,

Now I realized that the Pyramid is very complicated...
Sen Moc
User offline. Last seen 18 years 16 weeks ago. Offline
Joined: 30 Aug 2005
Posts: 123
Abdelmoneim Youss...
User offline. Last seen 8 years 33 weeks ago. Offline
Joined: 24 Oct 2004
Posts: 21
all the activities ID begin with ،°CM،± and in each activity with it own activity code named ،°MAJC،± (Major Code). Please use global change function to replace activity ID with first character ،°C،± and follow with the major code and serial number. Use the global change function to replace them.

The answer what،¯s the global change function that you wrote


Philip Jonker
User offline. Last seen 15 years 21 weeks ago. Offline
Joined: 7 Nov 2004
Posts: 852
Groups: None
Hi this is simple, create a code cale TEMP with a length of 10, and export this to a dbf file, then insert the new ID’s in this field and import. Thereafter do a global change
Raja Izat Raja Ib...
User offline. Last seen 12 years 48 weeks ago. Offline
Joined: 2 Jun 2005
Posts: 299
Yes edgar,
u callin me, thanks for your introduction, i dont have tips for U, this month.

Hi abdeel,
U can refer to previous Post Thread... in Primavera Project planner - P3> renumbering activity ID
Steven Oliver
User offline. Last seen 11 years 22 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Be extremely careful when changing activity id’s!

Using Global change, from memory, the syntax is something like

actid="A"&actid (to insert an "A" as a prefix)

You may need to run the trim function as well.

If you can be more descriptive of your problem, perhaps better advice can be given.
Edgar Ariete
User offline. Last seen 5 years 30 weeks ago. Offline
Joined: 17 Jul 2005
Posts: 184
If you don’t mind waiting...? I’ll just call Raja...(he got the answer I suppose).


cheers