Duration with decimal point...

5 replies [Last post]
Rick Aquino
User offline. Last seen 14 years 32 weeks ago. Offline
Joined: 6 Apr 2005
Posts: 48

Hi Guys,

How to set-up a planning unit in the duration with a decimal point, eg.2.3 days,2.4 days, etc etc,is that possible? i’m using "day" as my planning unit, (hrs, is not an option for me coz it’s a long project).

Thanks..

Replies

Gary Moffatt
User offline. Last seen 17 years 47 weeks ago. Offline
Joined: 30 Oct 2002
Posts: 4
Groups: None
Hi Rick,
The calculation in P3 works in whole units - your only option for parts of a day is hours, but you can run a secondary schedule, for example a steel erection schedule, and import or key in a summary level into your main schedule. Even if your client demands it as backup it will only detail one part of your work.
Dieter Wambach
User offline. Last seen 8 years 9 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Rick

No you can’t! I agree to Raviraj, without decimals should be ok for longer projects. In P3e it would be poosible but there too I didn’t use it - for longer projects.

Dieter
Rick Aquino
User offline. Last seen 14 years 32 weeks ago. Offline
Joined: 6 Apr 2005
Posts: 48
Hi Rav and Anoon,

Thanks for your immediate response, but is there a possibility that i could set up my duration with a decimal point? like 2.3 days, 2.4 days, etc, etc. because when i enter the duration with decimal point the primavera will round it off to a whole number, and when you organized it to see the schedule duration it is less of what i have planned.is there a possibility for p3 to accept whatever duration i encoded.
Thanks Again.
A D
User offline. Last seen 4 years 32 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Hi Rick,

If the project is long, why u want to put duration in hours. Do u want to be so transparent with ur client that u will activity worth in hours only.

Even, it is neither required by Client/Consultant nor by project team.

Hours are used in mostly maintenance projects, where shutdown means loosing money.

Its of no point in putting duartion in hours for a long project

Cheers,

Raviraj
Anoon Iimos
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
i suggest that you should never do that, if it’s day or hour so be it!