Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Decimal places in remaining duration field

7 replies [Last post]
Stuart Atkinson
User offline. Last seen 1 year 10 weeks ago. Offline
Joined: 16 Jan 2004
Posts: 68
Everyone,

I am currently running MSP 2007. The remaining duartion is to 2 decimal places in the summary fields ONLY. I have checked workdays in all calendars. Any suggestions to correct this.

Thanks in advance,

Stuart

Replies

Esther Pickett
User offline. Last seen 13 years 4 weeks ago. Offline
Joined: 24 Feb 2011
Posts: 4
Groups: None
blue host Colonialist split female libido gird horace fat cow hosting oscillogram setup acai berry select myocommas infuriate
Stuart Atkinson
User offline. Last seen 1 year 10 weeks ago. Offline
Joined: 16 Jan 2004
Posts: 68
Thanks Rajesh,

But Alex says it is fine.

Stuart
rajesh anand
User offline. Last seen 14 years 37 weeks ago. Offline
Joined: 5 Dec 2006
Posts: 27
Stuart,
Send me the file to rajesh_anand70@yahoo.com
I can do it for you

Regards,
Rajesh
Stuart Atkinson
User offline. Last seen 1 year 10 weeks ago. Offline
Joined: 16 Jan 2004
Posts: 68
Thanks Alex,

i will try that in the next few weeks.

Stuart
Stuart Atkinson
User offline. Last seen 1 year 10 weeks ago. Offline
Joined: 16 Jan 2004
Posts: 68
Alex,

i has the same duration. There are onlytwo claendars on this project.

Thanks,

Stuart