Planning Duration in Decimal Notation

2 replies [Last post]
Anchalee Jenpanitsub
User offline. Last seen 18 years 29 weeks ago. Offline
Joined: 30 Nov 2006
Posts: 3
Groups: None
Hi All,

If I set the planning unit to be month, how can I assign the duration in decimal notation? Now, if I assign duration 1.5 month, it’s will round up to 2.0 month automatically.

Ex.
Planning unit: Month
Duration: 1.5 months

Thanks,
Anchalee

Replies

Eugene K
User offline. Last seen 13 years 50 weeks ago. Offline
Joined: 18 Oct 2006
Posts: 47
Groups: GPC Malaysia
yes. In P3, planning unit (duration unit defined for a project) is meant to be the "smallest" unit of measurement for activities in your project. that is why cannot hv decimal.
same case when specifying DAY as the unit of duration, smallest unit is Day. So the question of half-day on Saturday is out the window...
Dayanidhi Dhandapany
User offline. Last seen 4 years 12 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
you can try to use planning units in weeks, then in the barchart lalyout try to arrange the scale in months. or else there is no choice to do it. only in MSP(i am not sure about other packages) you can display it like 1.5days or so.