S Curve - P3

13 replies [Last post]
J Venkatesh PMP P...
User offline. Last seen 12 years 6 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 52
Groups: GPC Qatar
Frnds,

I have completed a schedule without any cost / resource loading..

Now I want to see what would be the monthly progress % ( S Curve) of the project...

I find difficult to see this without cost / resource loading...

Is there anyway to find the S Curve..

cany anyone help me in this...

J

Replies

ulysses garcia
User offline. Last seen 14 years 21 weeks ago. Offline
Joined: 22 Aug 2005
Posts: 259
Groups: GPC Qatar
Hi jaya,

You made mention you have already allocated resoucres and cost to your schedule. to find s- curve more easy in tracking your progress, all you have to do firstly is to create a baseline to compare it to your current schedule which is data date. then in primavera p3 in tool menu,graphic, click resource & cost .if you want to see the overall cost or resource curve you may just type the command string as ?????? to the selection. However in Primavera P5 you may treat it in a dirrent way but basically homologous in nature. just go to Click menu Project, Tracking layout, resource usage then activity profile option, and set up your printing preferences to view your s-curve.

Uly
Pranab Kumar Deb
User offline. Last seen 4 years 3 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
DEAR ASHRAF AND AHMED,
THANK YOU BOTH FOR THE HELP
REGARDS
DEB
Ahmed Syed
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 27 Mar 2007
Posts: 21
Groups: None
Thanks Ashraf for your valuable tip.
Infact, I also encountered the same problem as Parnab. But, then I changed the syntax with ADD and it worked fine.
Cheers
Ahmed Syed
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 27 Mar 2007
Posts: 21
Groups: None
Hi Parnab
Just a little change in Ashraf’s syntax
Resouce +(ADD) R
rather EQ
Ashraf Jahangeer
User offline. Last seen 9 years 15 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Try this Deb,

1. Add Resource
If OD > 0 the RES AD R

Regards,

Ashraf
Pranab Kumar Deb
User offline. Last seen 4 years 3 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
hello ashraf i have done exactly as per your advice still it is not working , when i run 1 , it say no activities affected
regards
deb
Ashraf Jahangeer
User offline. Last seen 9 years 15 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Define the following Global Change.


1. Add Resource
If OD > 0 the Resourse = R

2. Modify Resurce

If OD > 0 then RDUR = OD


First run 1 and then run 2.

Regards,

Ashraf



Pranab Kumar Deb
User offline. Last seen 4 years 3 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291
hello ashraf but i am unable to assign this resource r to all activities
regards
deb
J Venkatesh PMP P...
User offline. Last seen 12 years 6 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 52
Groups: GPC Qatar
In MSP, to find the same..I will auto update the project keeping the data date as project end date considering all the activities are happened as well as planned..

After this, I can take the S - curve / Monthly progress happened from the Reports and will plot the S-Curve...But any option, like that wud available in P3

J
J Venkatesh PMP P...
User offline. Last seen 12 years 6 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 52
Groups: GPC Qatar
oops...I did it....

Ashraf and Bijaya....Thank u...Thank u very much

It worked well...

J
Bijaya Bajracharya
User offline. Last seen 9 years 9 weeks ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
S curve for what? Usually you will use it for resource (number or cost), or cost. If you don’t have those parameters in the programme and you still wish to see S curve, you need to think of something - and original duration as suggested by Ashraf is a very good idea. Just think of Original duration as a resource.

You can make an even simpler S curve. If you give your activty 1 point for starting and 1 point for finishing, you have two points each planned for every activity. In a number of occasions, even such an S curve comes as a very good project control tool. Now to get this curve in P3, you, of course need to create a resource S. You can then globally assign 2 units of it to all the activities.
J Venkatesh PMP P...
User offline. Last seen 12 years 6 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 52
Groups: GPC Qatar
Dear Ashraf,

Thanks for ur reply....

T s not clear,,,am not convinced....can u explain this or is there any other way available...

J
Ashraf Jahangeer
User offline. Last seen 9 years 15 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Jaya,

Define a resource named R.

Run Global change and add R to all activities.

Then run a global change Resource R = OD.

You can now get the desired S-Curves which will be based on OD.

Regards,

Ashraf