Splitting activities in P3

2 replies [Last post]
Khaleel Mohammad
User offline. Last seen 8 years 47 weeks ago. Offline
Joined: 21 Nov 2005
Posts: 9
Hi guys,
I had to switch from P3e/c to P3 3.1, i was trying to split an activity but had no idea how to do it, i have done it in MS Project, but would appreciate if anyone could suggest a way in P3.
tx

Replies

Rommel Ramirez
User offline. Last seen 14 years 49 weeks ago. Offline
Joined: 16 Mar 2007
Posts: 5
Groups: None
Guys,

Using the date has no effect on the splitting but adding its duration instead, Please try to create a separate calendar for that certain activity and make non-working date as you plan and then assign it afterwards.

Hope it’ll help.

Rgrds,
Mel
Jose Frade
User offline. Last seen 3 years 3 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None
Hello.

Go to Date form when in that activity and register a stop and restart dates.

Hope it helps.

BR
JMFrade