Splitting / Suspend /Resume Activity

2 replies [Last post]
Felis Muhammed
User offline. Last seen 4 years 25 weeks ago. Offline
Joined: 23 Jul 2006
Posts: 5
Groups: None
Hai all,

Is it possible to split an activity in P3 the way we do in MS-project?? Also how to suspend and resume an activity.

Appreciate your response.

Regards

Felis

Replies

Christian Adrian ...
User offline. Last seen 4 years 38 weeks ago. Offline
Joined: 3 Jun 2003
Posts: 193
Groups: None
using "suspend and resume date" should be dealth with caution, you can only use it on an activity which is active and has been affected with arising events not to prolong the schedule...

Cheers...
Karim Mounir
User offline. Last seen 9 years 36 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Splitting : select the activity u want and right click on it and select Dissolve / Extract.

Press F7 to show the bottom activity form
Suspend / Resume : select the activity in which u want to apply suspend or resume date then click on "Dates" then select the "Suspend" or "Resume" date.