Weighted % of activities

5 replies [Last post]
Alexander Bernardo
User offline. Last seen 12 years 14 weeks ago. Offline
Joined: 21 Sep 2005
Posts: 5
The schedule was prepared at excel and the equivalent weighted percentage of each activity was calculated accordingly basing on the the cost of each activity (labor and matl).

Now I am preparing at P3 but I can’t produce the desired result i.e. classic layout with weighted percentage to be shown on the report (bar chart).

Please, can somebody guide me how to do that.





Replies

bayou boy
User offline. Last seen 18 years 8 weeks ago. Offline
Joined: 16 May 2006
Posts: 8
please share the method you used to get the weighted % to show.

thanks
bb
Alexander Bernardo
User offline. Last seen 12 years 14 weeks ago. Offline
Joined: 21 Sep 2005
Posts: 5
Thanks everybody, got it.
Raja Izat Raja Ib...
User offline. Last seen 14 years 15 weeks ago. Offline
Joined: 2 Jun 2005
Posts: 299
Hi,
is the wtg more then 2 decimal, i believe its difficultif your wtg more then 2 decimal, i try once before. u have to divide by 1000 or 10000 if not it will become 0.00. Another thing itsdifficult to roun upthe numbers. somtimes it will more (eg 100.23) or less (eg 99.57).
Rey Basadre
User offline. Last seen 17 years 16 weeks ago. Offline
Joined: 5 Mar 2006
Posts: 24
What you want is possible. Make use any or combination of the following P3 utilities:
1. Report writer
2. Matrix/resource/cost report
3. Data customizing.

Arno Schoonaard
User offline. Last seen 9 years 7 weeks ago. Offline
Joined: 20 Apr 2004
Posts: 8
Create an activity code for it and put in there, make the activitycode visible in your layout.