The schedule was prepared at excel and the equivalent weighted percentage of each activity was calculated accordingly basing on the the cost of each activity (labor and matl).
Now I am preparing at P3 but I cant produce the desired result i.e. classic layout with weighted percentage to be shown on the report (bar chart).
Please, can somebody guide me how to do that.