No automatic scheduleding

3 replies [Last post]
Andrew Tan
User offline. Last seen 12 years 31 weeks ago. Offline
Joined: 9 Oct 2004
Posts: 40
Hi,
I wish to know/recall how to disable the scheduling function when I press F9.

I want the dataline to shift but not the end dates so that I can update the bar chart better for management viewing..

Please advise.

Replies

Frank Borcherdt
User offline. Last seen 8 years 38 weeks ago. Offline
Joined: 3 May 2001
Posts: 88
Groups: None
Andrew,

You can move the data date without scheduling through the Global calendars.

Highlight the Global calendar and click the standard button. Data date is an editable field in this form.

NOTE - if you schedule (press F9) then P3 uses this new date so using a target as discussed below is the better solution.

Not 100% sure what you are doing but thought I’d give this option as well
Daniel Limson
User offline. Last seen 6 years 6 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None
Andrew,

There is a way of doing this in P3. YOu need to set-up P3 to show progress against your target (baseline). Of course you need to show your target bar instead of your current bar. This will show progress against your target without moving the end dates.

Hope this helps.

Cheers,
Daniel
David Kelly
User offline. Last seen 3 years 5 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
andrew,

This cannot be done. The data date cannot be reset without scheduling.

You can use the attachment toolbar to drop a curtain, or a line, or indeed use the progress spotlight to highlight a date range.