Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Several subprojects with automatic resource shifting

1 reply [Last post]
Devamalya De
User offline. Last seen 5 years 24 weeks ago. Offline
Joined: 20 Oct 2005
Posts: 53
Groups: None

Dear all,

Plzzz let me know how to shift resouces automatically (if at all) among sevral subprojects in P3 whenever the resource levels reach a certain threshold value. Wanting to hear from you all experts in P3.

Replies

Rashid Iqbal
User offline. Last seen 17 years 3 weeks ago. Offline
Joined: 3 May 2005
Posts: 94
Groups: None
Hi,

Version 5 could somewhat level the resources on different project based on assigned priorities. Though, in my view the leveling capabilities of that version are not comparable to P3.

Regards