Forum Sponsor:

An innovation in P6 Professional training from RPCuk in partnership with Oracle. All the topics that matter to you in workshops customised to your role and industry.  Now get superior training value when you book our Blended Learning Bundle. Learn more here.

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Particular Resource assignment automatically in Primavera among the group of Resources

3 replies [Last post]
Rama Chandran
User offline. Last seen 2 years 26 weeks ago. Offline
Joined: 18 Dec 2011
Posts: 10

Hi

Need your support here.

This is related to Manufacturing planning works.

Activity A (Machining operation) - 15 days

Activity B (Machining operation) - 10 days

Activity C (Machining operation) - 20 days

Activity D (Machining operation) - 25 days

Activity E (Machining operation) - 5 days

Activity F (Machining operation) -  5 days.

 

All above activities were independent. We are having two resources say LATHE 1 and LATHE 2. Is is possible in Primavera , assigning a resource (either LATHE 1 or LATHE 2) automatically based on the resource availability to get better results (Shortest Project duration).

 

Thanks in advance

Ram

Replies

Zoltan Palffy
User offline. Last seen 16 hours 48 min ago. Offline
Joined: 13 Jul 2009
Posts: 2408
Groups: None

no

David Kelly
User offline. Last seen 7 weeks 20 hours ago. Offline
Joined: 19 Oct 2004
Posts: 563

Rama,

 

Primavera has no mechanism for automatically assigning resources. 

This is called Skill Scheduling.

I also expect that your resources may have different production rates and that you would like to use norms and measure your works in physical units, etc.

If you need this functionaity try Spider Project.