Particular Resource assignment automatically in Primavera among the group of Resources

3 replies [Last post]
Rama Chandran
User offline. Last seen 7 years 5 weeks ago. Offline
Joined: 18 Dec 2011
Posts: 10

Hi

Need your support here.

This is related to Manufacturing planning works.

Activity A (Machining operation) - 15 days

Activity B (Machining operation) - 10 days

Activity C (Machining operation) - 20 days

Activity D (Machining operation) - 25 days

Activity E (Machining operation) - 5 days

Activity F (Machining operation) -  5 days.

 

All above activities were independent. We are having two resources say LATHE 1 and LATHE 2. Is is possible in Primavera , assigning a resource (either LATHE 1 or LATHE 2) automatically based on the resource availability to get better results (Shortest Project duration).

 

Thanks in advance

Ram

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

no

David Kelly
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

Rama,

 

Primavera has no mechanism for automatically assigning resources. 

This is called Skill Scheduling.

I also expect that your resources may have different production rates and that you would like to use norms and measure your works in physical units, etc.

If you need this functionaity try Spider Project.