This is related to Manufacturing planning works.
Activity A (Machining operation) - 15 days
Activity B (Machining operation) - 10 days
Activity C (Machining operation) - 20 days
Activity D (Machining operation) - 25 days
Activity E (Machining operation) - 5 days
Activity F (Machining operation) - 5 days.
All above activities were independent. We are having two resources say LATHE 1 and LATHE 2. Is is possible in Primavera , assigning a resource (either LATHE 1 or LATHE 2) automatically based on the resource availability to get better results (Shortest Project duration).
Thanks in advance