Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

linking automatically after fragnet

1 reply [Last post]
Vijayendra Surve
User offline. Last seen 10 years 43 weeks ago. Offline
Joined: 5 May 2007
Posts: 20
Groups: None
sir,
for typical floors take 52 floors once we copy activities n fragnet links r there but after retreving if one of links needs to b changed is there any other way to do tht for all 52 floors by global change or something.
Also if i want to insert/merge activities (wth links) in revised progg. how should tht be done.

Replies

Mangesh Khuspe
User offline. Last seen 26 weeks 6 days ago. Offline
Joined: 10 Apr 2007
Posts: 162
hi
just put on your mail id
i will sent u some thing to read on using fragnets
regrads
mangesh