Assigning resource curves

3 replies [Last post]
Eckart Schenck
User offline. Last seen 4 years 10 weeks ago. Offline
Joined: 25 May 2005
Posts: 28
Groups: None
Hi guys,

I’ve got to change the resource curve of a number of activities. Now using xls import P3 creates a new resource instead of updating the existing one.

Any ideas?

Thanks
Heinz

Replies

DATTATREYA PADHARTHI
User offline. Last seen 5 years 21 weeks ago. Offline
Joined: 18 Apr 2003
Posts: 90
Absolutely, if you have just one resource & you decide to change the curve based on your gut feeling, experience etc, you can do so by showing " Resource curve" columns.

If you have more than one resources , resource curve columns will be empty.
& if you have to change curves based on type of resources, groupings , codes etc (in an intelligent way) it is advisable to do so thru Global Change. Better Go for Global Change.

Dattatreya
Jaco Stadler
User offline. Last seen 17 years 28 weeks ago. Offline
Joined: 9 Sep 2004
Posts: 299
Groups: None
Why Export.

In p3 Organise by Resource. Show Column BQ & Curve. and Do it in P3.
Bill Guthrie
User offline. Last seen 7 years 50 weeks ago. Offline
Joined: 14 Mar 2005
Posts: 262
yes
first export existing resources.

make changes then import. be sure that all resources on the xls sheet are loaded in p3.

should be easy