Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P3 SCHEDULES IN ARBITRATION & COURT CASES

2 replies [Last post]
Kris Harry
User offline. Last seen 12 years 36 weeks ago. Offline
Joined: 4 Oct 2004
Posts: 47
Groups: None
Dear Friends,

Can P3 schedules be presented in arbitration and court cases. Are such schedules taken as evidence. Any experiences of you guys

Replies

Richard Brodit
User offline. Last seen 16 years 24 weeks ago. Offline
Joined: 1 Feb 2002
Posts: 9
Groups: None
Dear Kris,

Yes, P3 schedules can be used in arbitration cases provided that this document has been acknowledged and accepted by the other party (that means if you have submitted a Preliminary Works Programme and it has been accepted by the Client as your Programme or vice versa , if you are the client and you accepted your contractor’s programme and there is deviation either in your side or their side and a case is made against it, yes, this P3 schedule can be a legal and binding document)

But sometimes, there are clauses in the contracts which specifies that "Programme does not form part of the legal contract, and it is for information only" pls. check this.

Regards,

Richard
Dayanidhi Dhandapany
User offline. Last seen 3 years 5 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
Dear Kris,

Definitely P3 schedules can be presented in arbitration and court cases. It will be used as a evidence.

Regards

Daya