Has your question already been answered?

Get a quicker response; before you post, why not search to see if it has already been answered

Interactive Planning Session Question

4 replies [Last post]
Ryan Jarreau
User offline. Last seen 3 weeks 2 hours ago. Offline
Joined: 5 Feb 2018
Posts: 3
Groups: None

A few times a month, I facilitate interactive planning sessions between owners and subcontracted engineers and constructors. Normally ill print out a big paper timeline, hadwrite activity descriptions on post it notes and positon them on the timeline before the meeting starts. During the course of the discussion, we'll move the post it notes around to create our baseline plan. After the meeting, I'll input the information into P6 with logic, durations, and resources. At that point our baseline schedeule is created.


To me it seems a little unprofessional to handwrite on post it notes, but that's the standard at the company I'm working for. Is there a better way to do this? Does anyone have any tips on how to make an interactive planning session more efficent?


Thanks in advance!


ade afe
User offline. Last seen 1 week 4 days ago. Offline
Joined: 4 Mar 2018
Posts: 5
Groups: None

Apologies, wrong post

Zoltan Palffy
User offline. Last seen 1 day 6 hours ago. Offline
Joined: 13 Jul 2009
Posts: 1696
Santosh Bhat
User offline. Last seen 19 hours 59 min ago. Offline
Joined: 15 Apr 2005
Posts: 74

Use a more collaborative Planning and scheduling tool like Netpoint by PMA Technologies.

Mike Testro
User offline. Last seen 10 hours 9 min ago. Offline
Joined: 14 Dec 2005
Posts: 4305

Hi Ryan

You are describing the "Lean Planning" process which has its use except that you have to do it all over again the next week because nobody actually pays any attention to what the planner says.

BTW you forgot to mention the pins and string.

Best regards

Mike Testro